12441923C0039: This Project Includes Reconstruction of the Pr-191 Main Water Distribution System. the Work Includes Installation of Approximately Three Miles of Hdpe Waterline. Much of the Waterline Is Along Puerto Rico Highway 191 and Will Require Traffic Control.
Awarded to Advantix Engineering Corp by Forest Service.
$3.1Mobligated
$3.1Mpotential value
25 September 2026current end date
See modifications, all subcontractors and funding in FedSift →
| Contract | 12441923C0039 |
|---|---|
| Awardee | Advantix Engineering Corp |
| Awarding agency | Forest Service |
| Awarding office | USDA FOREST SERVICE-SPOC EAST |
| NAICS | 221310 Water Supply and Irrigation Systems |
| PSC | Y1NE Construction of Water Supply Facilities |
| Place of performance | PR |
| Offers received | 2 |
| Period of performance | 28 September 2023 to 25 September 2026 |
| Potential end | 25 September 2026 |