Contracts › W912P525C1001
W912P525C1001: Wolf Creek Powerplant Generator Step-Up Unit (GSU) Transformer Replacement Project
Awarded to Yellowstone Electric Co by Department of the Army.
$30.6Mobligated
$45.4Mpotential value
01 January 2029current end date
See modifications, all subcontractors and funding in FedSift →
| Contract | W912P525C1001 |
|---|---|
| Awardee | Yellowstone Electric Co |
| Awarding agency | Department of the Army |
| Awarding office | W072 ENDIST NASHVILLE |
| NAICS | 335311 Power, Distribution, and Specialty Transformer Manufacturing |
| PSC | N061 Installation of Equipment- Electric Wire and Power Distribution Equipment |
| Place of performance | KY |
| Offers received | 2 |
| Period of performance | 20 March 2025 to 01 January 2029 |
| Potential end | 20 August 2030 |
| Estimated recompete solicitation | ~Q3 2028 (estimate, ~6 months before expiry) |
Source: USASpending.gov (FPDS), public federal procurement data, as the agency reported it. Our record updated 04 October 2026. The solicitation date is an estimate from the end date, not a posted date.
Other expiring 335311 contracts · All expiring contracts · USASpending record