Z1DA--612A4-19-016 | Renovate Outpatient Pharmacy and HVAC

VETERANS AFFAIRS, DEPARTMENT OF · Solicitation 36C26126R0036 · NAICS 236220 · Unrestricted (full and open) · Closed

Solicitation details

Solicitation number36C26126R0036
Notice IDc6d4683b1df847ffbee4dc60be5b32cb
AgencyVETERANS AFFAIRS, DEPARTMENT OF
Sub-tierVETERANS AFFAIRS, DEPARTMENT OF
Contracting office261-NETWORK CONTRACT OFFICE 21 (36C261)
NAICS code236220
Product / service code (PSC)Z1DA
Set-asideUnrestricted (full and open)
Notice typeSolicitation
Posted03 September 2026
Response deadline20 July 2026 (closed)

Description

AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO. CONTINUATION PAGE 2 SOLICITATION NO: 36C26126R0036 ORDER NO: AMENDMENT NO: 0005 14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED) The purpose of this amendment is to answer three additional RFIs. Section 01 00 00 requires the project schedule to include a minimum of forty-five (45) days for VA relocation of Pharmacy Services into the completed temporary facilities, and a minimum of forty-five (45) days for VA relocation of staff, equipment, and operations from the temporary facilities back into Building 650 upon completion of the renovated outpatient pharmacy suite. Please confirm: (a) whether both 45-day VA relocation periods are included within the 540-calendar-day period of performance; and (b) whether contract completion for purposes of the period of performance is measured at Government acceptance of the renovated pharmacy suite, or upon completion of temporary facility removal and complete site restoration following the VA's 45-day relocation back into Building 650. ANSWER: The 540-calendar-day Contract Time includes both 45-calendar-day VA relocation periods. Contract completion is achieved upon completion of all Contract Work, including removal of the temporary facilities and complete site restoration following the VA's final relocation back into Building 650. "Construction start date" refers to commencement of on-site construction activities, including temporary facility construction. This requirement applies to construction-phase submittals required to perform the Work and does not include closeout submittals (e.g., O&M manuals, as-built drawings) or finish selections not required before installation. Section 01 00 00 states: 100% of ALL project submittals shall be approved prior to the construction start date. Please clarify whether construction start date refers to (a) commencement of temporary facility construction, or (b) commencement of renovation work within Building 650. Please also confirm whether closeout-phase submittals (e.g., O&M manuals, as-built drawings) and late-phase finish material submittals are included in this requirement, or whether it applies to construction-phase submittals only. GLBA appreciates the Government's attention to these questions and remains available for any clarification needed. ANSWER: "Construction start date" refers to commencement of on-site construction activities, including temporary facility construction. This requirement applies to construction-phase submittals required to perform the Work and does not include closeout submittals (e.g., O&M manuals, as-built drawings) or finish selections not required before installation. One of our drywall trade partners has brought up a conflict they have found on the existing walls at the perimeter of the pharmacy. Per wall type Mbb3 on Sheet A-501 at the corridor it appears that the framing is existing and one new layer of board, the security mesh fire safing and a closure angle is required to be installed. How we would install the 3 slip track at an existing wall? Are they to be cut between the existing studs and fastened to the bottom of the roof deck? Please advise if the slip track is needed. ANSWER: Install the head-of-wall/slip-track assembly at the existing wall by attaching the slip track to the structure above as required to maintain the specified assembly. Existing studs are not required to be removed or modified except as necessary to complete the installation. ///////////////////////////////////////////////LAST ITEM//////////////////////////////////////////////////

Go deeper on this solicitation

FedSift reads the full solicitation package — every attachment — and pre-extracts the compliance matrix, evaluation factors, key risks, win themes and deal-breakers, each with a verbatim quote and the exact PDF page it came from. It scores the opportunity against your company profile, tells you whether to bid as prime or sub, and ranks teaming partners who could close your gaps.

Open the AI analysis in FedSift →

Free forever plan — no credit card. Browse solicitations without an account; sign in for AI analysis and matching.

Other open solicitations in NAICS 236220

All NAICS 236220 solicitations →

More from VETERANS AFFAIRS, DEPARTMENT OF

All VETERANS AFFAIRS, DEPARTMENT OF solicitations →

Source: this notice on SAM.gov. FedSift republishes public federal procurement data and is not affiliated with the U.S. Government. Always confirm dates and requirements against SAM.gov before responding.