South Bay International Wastewater Treatment Plant (SBIWTP) Rehabilitation and Expansion Progressive Design-Build (PDB)

Inactive on SAM.gov · Unrestricted (full and open) · International Boundary and Water Commission: U.S.-Mexico · San Ysidro, CA · NAICS 237110 · Solicitation 191BWC24C0008P00012

Following NAICS 237110? Get new solicitations in it by email as they post — no account needed.

Email me new ones

What happened next

This is SAM.gov's award notice for this solicitation.

Awarded to PCL Construction Inc. dba PCL Construction Services Tempe AZ 85284 USA for $552.4M, posted 13 October 2026.

Solicitation details

Solicitation number191BWC24C0008P00012
Notice IDfb3dc2bfe38f4cadad0b01ec41e87e68
AgencyInternational Boundary and Water Commission: U.S.-Mexico
Contracting officeINTERNAT. BOUNDARY AND WATER COMM.
NAICS code237110 — Water and Sewer Line and Related Structures Construction
Product / service code (PSC)Y1ND
Set-asideUnrestricted (full and open)
Notice typeAward Notice
Posted13 October 2026
Response deadlineNot stated
Place of performanceSan Ysidro, CA, USA
CompetitionCompetitive

Get new NAICS 237110 solicitations by email

This one has closed. We'll email you when new NAICS 237110 (Water and Sewer Line and Related Structures Construction) solicitations post — the first email lists what is open right now, then at most once a week, only when something new posts. No account needed; unsubscribe in a click.

Description

The purpose of this modification is to incorporate additional construction packages and Phase 1 expansion work into the progressive design-build contract. The modification adds the following construction packages: Early Work Package (EWP) 1C Replacement In Kind Final Construction Price: $13,147,453 Scope includes: Removal and replacement of existing roofs. Replacement of process equipment and piping. Replacement of electrical equipment. Replacement of odor control media. Installation of new window sealants. Replacement of coiling doors. Replacement of emergency showers and eyewashes. Painting and coating of existing facilities. Early Work Package (EWP) 3B Early Procurement Final Construction Price: $25,693,528 Scope includes procurement of critical long-lead equipment, including: Standby generators and associated switchgear. Medium-voltage switchgear. Positive displacement blowers. Submersible solids-handling pumps. Dewatering centrifuges. Stainless steel slide gates. Stop logs. Early Work Package (EWP) 4 Major Concrete Structures Final Construction Price: $37,468,188 Scope includes: Construction of major concrete structures for new Headworks facilities. Primary Sedimentation Tanks 6 and 7. Storage Warehouse. New influent and drainage infrastructure. Associated piping, carpentry, architectural, mechanical, electrical, and support features. Phase 1 Base Construction Expansion Final Construction Price: $369,613,306 Scope includes: New Headworks facility with integrated pump station. Screening and grit removal systems. Primary sedimentation expansion. Centralized odor control facilities. Waste activated sludge thickening and storage facilities. Dewatering upgrades. Lime storage/feed and truck loadout facilities. Storage warehouse. Chlorination storage facility. Administrative building expansion. Multiple electrical buildings. New electrical service, generators, utility distribution systems, process piping, and site work. Rehabilitation of existing activated sludge tanks and lime silos. Engineering services during construction and procurement of the effluent meter and bypass piping. Construction Allowances The contract also increases CLIN 008 Construction Allowances by $9,804,886, increasing the allowance amount from $1,783,374 to $11,588,260 to address uncertain construction elements and field conditions associated with EWP-1C and Phase 1 construction activities. [191BWC24C0008 P00012 | PDF] Period of Performance The base construction period of performance has been revised to 1,643 calendar days (54 months) from issuance of the Base Construction Notice to Proceed (NTP). Construction closeout requirements remain unchanged and must be completed within 180 calendar days following construction completion. Award Value Previous Contract Value: $106,449,546 Modification Increase: $445,922,475 Revised Total Contract Value: $552,372,021

Go deeper on this solicitation

FedSift reads the full solicitation package — every attachment — and pre-extracts the compliance matrix, evaluation factors, key risks, win themes and deal-breakers, each with a verbatim quote and the exact PDF page it came from. It scores the opportunity against your company profile, tells you whether to bid as prime or sub, and ranks teaming partners who could close your gaps.

Open the AI analysis in FedSift →

Free forever plan — no credit card. Browse solicitations without an account; sign in for AI analysis and matching.

Other open solicitations in NAICS 237110

All NAICS 237110 solicitations →

More from International Boundary and Water Commission: U.S.-Mexico

All International Boundary and Water Commission: U.S.-Mexico solicitations →

Source: this notice on SAM.gov. FedSift republishes public federal procurement data and is not affiliated with the U.S. Government. Always confirm dates and requirements against SAM.gov before responding.

FedSift turns SAM.gov and USASpending data into federal BD intelligence — smart matches, recompete radar, cited AI solicitation analysis and compliance matrices.

Source data: SAM.gov (solicitations) and USASpending.gov (awards), refreshed nightly. FedSift is not affiliated with the U.S. Government.